Marceline Swimming Pool
Marceline, MO
The City of Marceline chose the Carrothers/Larkin Design Build Team for their new swimming pool. Construction started in Fall of 2016 and the new pool was opened in May 2017.
Our Design Build services included:
- Initial planning meetings with the city council and staff to discuss general concept
- Development of several general concepts with budget costs / impact
- Narrowing of general concept for presentation to general public
- Prepare fliers and concept boards for public presentations
- Attend / conduct multiple town hall meetings to generate public interest
- Additional efforts for a dual election—bond issue and sales tax increase. One in the fall of 2015 and one in the spring of 2016. Both passed
- Post-election: work with the city to finalize the project design to meet budget constraints
- Construction of the new pool and bathhouse